Introduction

Odvantage were proud to support the National Highways Smart Motorway Programme (SMP) and provide Project Director support services on the flagship M4 J3-12 project.

The M4 forms a vital part of the UK road network, serving as the main strategic route between London, the West of England and Wales. This route has continually evolved since the first section opened in 1959, with the English section completed in 1971, followed by the Welsh section in 1993. Several urban areas in the south east region rely on the M4 between for connectivity, including Reading, Maidenhead, Windsor, Slough and Hayes. Other transport hubs and tourist attractions also rely on this stretch of the M4, including Heathrow Airport, Twickenham, Windsor Castle and Legoland. It connects people, communities and businesses, carrying on average 130,000 vehicles per day, and is an essential transport link for the local area and the UK as a whole.

A smart motorway was the next step in the evolution and enhancement of the M4, supporting the local, regional and national economic growth agendas. As the largest smart motorway scheme in England, by value and length, its scale and constraints (including a Development Consent Order or DCO) necessitated a different delivery vision.

M4 J3-12 Smart Motorway

Portfolio: Significant Projects

Client: National Highways

Sector: Highways

Capabilities: Portfolio, Programme and Project Delivery; Trusted Advisor

Challenge: A flagship 52km scheme, and the only smart motorway that necessitated formal consent by the Planning Inspectorate, the project faced significant pressures, with an emerging forecast £180M beyond the funded position. There was a clear need to critically examine all facets of delivery and chart a path to recovery.

Solution: Odvantage provided strategic leadership, the critical link between the client’s vision and the realities of a major project, unifying diverse perspectives through constructive partner liaison and positive stakeholder dialogue, ensuring the project remained correctly configured to achieve a broad spectrum of expectations.

Key Outcome: project delivered within budget, with exemplary performance against safety, quality and customer metrics.

Timeframe: 2020-2025

Challenge

Classified as a ‘Tier 1’ project, the scheme was anticipated to incur whole-life costs above £500 million, intricate designs, multiple stakeholders, and substantial risks. As much of the M4 was originally built as a dual two-lane carriageway (D2M), evolving the route to meet the demands of the 21st century was challenging:

  • 102km of new smart motorway capacity
  • 34 new high visibility emergency areas for customer use
  • 11 existing bridges to be demolished, impacting local traffic networks
  • 11 new bridges to be built alongside neighbours and communities
  • 2 existing bridges widened whilst remaining operational, carrying motorway traffic over railways, rivers and roads
  • 150 km of new drainage, adapting infrastructure for climate change
  • 63 km of new concrete central safety barrier, enhancing customer safety
  • 22 km of new environmental noise barrier, minimising impacts on communities
  • 158 new gantries, enabling signalling to keep customers informed and safe
  • 865 new road signs, ensuring drivers are kept informed and updated
  • 130,000 new trees and plants, mitigating impacts on neighbours

Early challenges generated a need to work differently, migrating away from transactional supply contracts towards an enterprise alliance way of working. Package 1 (J8/9-12) had suffered from late identification of errors, omissions, clashes, ambiguities and clarifications, generating safety and quality consequences which impacted on time and cost. At the point Odvantage were engaged, the project was facing significant pressure, with an emerging forecast £180M beyond the funded position. There was a clear need to critically examine all facets of delivery, and chart a path to recovery.

Opportunity

Odvantage were tasked with providing strategic leadership counsel to the project team to achieve efficient project delivery. Our role provided the crucial link between the client’s vision and the stark reality of a major design and construction undertaking. As an already mature project when we were engaged, we worked with the partners to reinforce a unified ‘One Team’ approach, achieving clarity on objectives and expectations in terms of relationships, ways of working, and how we intended the new arrangements to operate in practice.

M4 CSB

Our involvement provided an opportunity for fresh perspective on the technical, institutional and financial pressures that major projects face. With a multitude of stakeholders, our role as a guardian of the project vision was key in unlocking opportunities to enable the project and the partners to achieve successful outputs:

  • work with the team to challenge the efficacy and efficiency of solutions, taking account of the technical requirements of the smart motorway, and the impact on neighbours and communities;
  • engage with stakeholders and customers, who may have envisioned different versions of the project based on the details available in the DCO;
  • validate expectations that the entirety of the asset base merited renewal due to its proximity to a major project;
  • verify scope, and the management of change, to make a real difference to a project with lengthy development and construction durations;

deliver not only a safe work environment, but a safe and serviceable

Outputs Delivered

Overhead gantry signs on M4 motorway near Maidenhead

With significant stakeholder interest in smart motorways, the project was delivered under a renewed level of public scrutiny. We worked in concert with multiple organisations to gain the widest spectrum of project perspectives, then aimed to enhance understanding of the overall smart motorway product and change perceptions of delivery. Key outputs delivered through our input included:

  • safety leadership engagement with design offices, improving the connection between design choices and construction safety outcomes;
  • an independent maturity assessment of the deliverability of Package 2 (J3-8/9), to ensure that the design provided a sufficient level of detail to generate safe and efficient construction;
  • constructive liaison with the delivery partners, critically reviewing sequencing and logistics with roadspace availability and customer expectations;
  • transparent briefings with DfT, Transport Focus and the Design Council, to aid understanding of the integration and interfacing of products to simplify smart motorway understanding, compliance for users, and product legacy;
  • positive dialogue with asset owners, National Highways and local authorities, on whole life considerations and scope, challenging the concept that replacing ageing assets was a necessary requirement to enable functionality;
  • regular conversations with neighbours, recognising that environmental mitigation to a predetermined design occasionally requires assessment from an outside perspective, and not being afraid to adapt if necessary;
  • starting at the finish, understanding that successful handback commences at initial handover, and not walking away once a project opens for traffic, we ensured that the project was correctly configured for the operational acceptance of the various owners.

Outcomes Achieved

Drone photo of Slough

The project had to navigate delivery alongside seismic events, including Covid-19 lockdowns and Royal Funerals, with sensitivity and respect. Through regular, proactive engagement with the numerous stakeholders, the team were able to react with positivity and agility to these challenges and still deliver to time and budget, achieving the following outcomes:

Helth, Safety, Wellbeingover 10M hours worked without significant incident
Customer experience

90%+ satisfaction (roadworks, information)

Investment£929.1m (max. £40m per month)
Smart Motorway Programme
How do you rapidly scale to successfully deliver 25% of capital funding settlement with a 400% increase in annual activity, and achieve a series of tangible metrics in safety, customer and delivery performance within a 5 year period?
Eye Digital Data - AI Artificial Intelligence and program code
If numerous global and local factors have conspired to erode delivery efficiencies, with projects effectively running just to stand still, maybe a fresh perspective can help to unlock potential savings that were otherwise hidden or overlooked?
Dublin, Ireland - February 13, 2019: Irish electric tram that parks in front of Heuston train station in the city center on a winter day
Major Projects Advisory Group
Against the backdrop of significant population growth, an ageing asset base, and well publicised cost escalation and late delivery of major projects, how can you enable better infrastructure decisions and regain public confidence in the system?
Aerial view of a power generating windturbine on a sunny day in  Denmark
Isle of Man
When a Crown Dependency is grappling with the challenge of ageing infrastructure, resource limitations, geographic constraints, and a reliance on neighbours, how do you use constructive scrutiny and coaching to improve capacity and capability?
Transport for London
Transport for London
What benefit are critical friends and independent advisors when the impact of a global pandemic has brutally exposed the vulnerability of the funding model, yet you still need to invest in infrastructure because ‘every journey matters’?
Overhead gantry signs on M4 motorway near Maidenhead
M4 J3-J12 Smart Motorway
When the longest, most intricate smart motorway project is facing significant budget pressures, you’ve got the majority of the complex works still to complete, and there’s a pandemic around the corner, where should you even begin?

Testimonials

"A true team player and a fantastic engineer, Barry O’Driscoll is diligent, committed and passionate."

Michael Nolan (Chair, Major Projects Advisory Group for the Government of Ireland. Former CEO, Transport Infrastructure Ireland)

"I worked closely with Barry O’Driscoll as part of the Senior Leadership Team (SLT) for the National Highways Smart Motorways Programme."

Mike Grant (Capital Delivery Director, Southern Water. Former Delivery Director, National Highways)

"Barry O’Driscoll has been one of nine trustees on the board for Citizens Advice, Stroud & Cotswold District, since 2021. We recently elected him to serve for another three years."

Elizabeth Hall (Chief Executive Officer, Citizens Advice Stroud & Cotswold District)

"I had the privilege of supporting Barry O’ Driscoll to deliver a major framework bid for a global engineering consultancy. As Bid Director, Barry created a ‘one team’ ethos from the start. "

Honor Morris (author and coach)

"Barry O’Driscoll is a man who leads from the front, inspiring those he works with to manage with commitment, honesty and ownership. "

Nick Simmonds-Screech (Project Director, European Data Centres. Former Project Director, A30 Chiverton to Carland Cross, National Highways)

Odvantage Ltd Logo - white

Would you like to see how we
contribute to a better world?

Contact

TEL +44 (0)7920 205808

Offices

11 Weavers Close, Dursley, Gloucestershire, GL11 4LR

Proud Member of the HIVE CoLab

Copyright © 2025 ODVANTAGE : Website Design & Hosting by Featherkite